We’re installing two packaging cells next week on a two-week window, and I need to drive the timeline hard without compromising floor safety. For those who’ve run fast rollouts, what’s your best lever to protect takt (LOTO at every changeover, 15-minute start-of-shift stand-ups, E-stop checks) without slipping the date?
Make “LOTO at every changeover” the first gate in a 10‑minute permit-to-run at each power-up; one named owner with stop-the-line authority, then E-stop and guarding checks before release… Keep the 15‑minute stand-up, but shift problem-solving to a rolling war room so the cell never idles; do you have day-by-hour hold points for first article in week one?